MRA CP 0266 - Delay to implementation date of MRA CP 0262

Current Status Rejected Implementation Date N/A
Version Related Changes MRA CP 266A

Executive Summary

This CP seeks to delay the implementation date of MRA CP 0262 to 5th November 2020 as a result of the impact businesses are experiencing due to COVID-19. Proposed Implementation Date: 04/06/2020

Change History

28 Apr 2020
MDB_20_0428 (Impact Assessment)
13 May 2020
MDB_20_0513 (For Vote)
13 May 2020
MDB_20_0513 (Accepted)

Related Documents