MAP CP 0331 - Delay to the implementation of MAP CP 0322 and MAP CP 0323

Current Status Rejected Implementation Date N/A
Version Related Changes MAP CP 0331A

Executive Summary

This CP seeks to delay the implementation date of MAP CP 0322 and MAP CP 0323 to 5th November 2020 as a result of the impact businesses are experiencing due to COVID-19. Implementation Date: 04/06/2020

Change History

28 Apr 2020
MEC_20_0428 (For IA)
13 May 2020
MDB_20_0513 (For Vote)
13 May 2020
MDB_20_0513 (Accepted)