MIF 278 - Gap with HH Change of Meter Operator Process

Current Status Closed Implementation Date N/A
Version 1.0 Related Changes

Executive Summary

Within the D0268 (Half Hourly Meter Technical Details) Data Flow the Manufacturers Make and Type is optional. However, it is mandatory on the subsequent D0303 (Notification of Meter Operator, Supplier and Metering Assets installed / removed by the MOP to the MAP). Therefore, this could mean a Meter Operator has to occur a site visit cost to find the manufacturers make and type to inform the Meter Asset Provider (MAP) they have gained the site.

Change History

No changes

Related Documents