DTC CP 3395 - Notifying the Meter Operator of the identity of the gaining Supplier on a CoS loss

Current Status Implemented Implementation Date 01/04/2014
Version Related Changes

Executive Summary

The Government response to the consultation on the Foundation Smart Market published on the 10th May included a decision on a proposed licence condition that mandates that the losing Supplier must notify the MAP of the CoS date and the identity of the gaining Supplier for the equipment that MAP is responsible for. The licence obligation (which is available in draft) only applies to SMETS compliant meters installed at domestic premises. Ofgem have confirmed that this obligation can be delivered by Suppliers through their MOP agents.

Change History

No changes

Related Documents