Current Status | Implemented | Implementation Date | 27/06/2019 |
---|---|---|---|
Version | 1 | Related Changes |
Executive Summary
This CP proposes shortening the Distribution Business response time for logical disconnections in MRA Agreed Procedure (MAP) 21, Disconnections, from 60 Working Days (WDs) to 5 WDs and clarifies that the obligation on Distribution Businesses to check for Related Metering Points prior to confirming disconnection is an obligation to check the data held in MPAS.Change History
25 Apr 2019
MDB_19_0425 (Impact Assessment)
30 May 2019
MDB_19_0530 (Accepted)