MDB was held on 28th April 2016. The table below shows the Change Proposals, voting outcomes and implementation dates.

Summary Implementation Date Outcome
MRA CP 0236 – Restricting the number of registration attempts made by a supplier –

This CP seeks to limit the amount of registration attempts to gain a customer to four.

3rd November 2016 Re-circulated for Impact Assessment
MAP CP 0271 – Updating MAP 13 –

MAP CP 0271 seeks to introduce the Point of Acquisition (PoA) model into MAP 13, align the Debt Assignment Protocol (DAP) Data Flow definitions and examples with those defined in Annex C of the Data Transfer Catalogues and remove a number of outdated references and appendices

3rd November 2016 Accept Modified
MAP CP 0272 – Removing MAPs 19, 22 and 23 from the MRA product set –

MAP CP 0272 seeks to removed MAPs 19, 22 and 23 from the MRA product set whilst the MAPs continue to be available for reference on the MRASCo website

30th June 2016 Accepted
MAP CP 0270 – Comparison of Meter Operator and ECOES data –

MAP CP 0270 seeks to introduce a new MRA Agreed Procedure (MAP) to mandate a data comparison exercise for Meter Information held on Meter Operator (MOp) systems and the Electricity Central Online Enquiry Service (ECOES).

3rd November 2016 Accepted
ECO CP 0169 – ECOES Automated Password Reset Function –

This change seeks to add functionality for ECOES users to be able to reset their own passwords

3rd November 2016 Re-circulated for Impact Assessment